Overview for Traditional ROW Maps
Once ROW map revisions are complete,
all
new ROW is acquired, and all
documents are recorded, upload
original PDF of the ROW map marked "FINAL MAP" to ROW Division via OnBase
. For the final map to be complete, it must contain:
- all project numbers;
- grantors' names;
- areas of acquired parcels;
- recording information;
- a "U" number assigned for utility adjustments/accommodations;
- names of the utility owner(s) and recording data for recorded documents, when applicable;
- at least one signature and date;
- DGN graphicsfiles;and
- GISfiles, if available.
Verification of the above list can be done by any of the following:
- District Surveyor
- Right of Way District Manager
- Utility Coordinator
- Right of Way or District Records Coordinators
Completing this process will minimize district
and division staff
time spent researching ROW maps.