Monday, February 2 to Friday, February 6
9 a.m. to 4 p.m. (as needed)
- SH-178 (Artcraft) east- and westbound between New Mexico State Line and Doniphan alternate lane closures
Crews will be working on illumination and wall installations.
- North Desert between Helen of Troy and Cheddars Restaurant alternate lane closures
- South Desert between Charlie Clark Nissan and Blue Sky alternate lane closures
Crews will be loading and unloading material and equipment.
Borderland Expressway Phase 2
Monday, February 2 to Friday, February 6
7 a.m. to 5 p.m.
- US-54 east- and westbound between Mesquite Hills and McCombs alternate lane closures
- Mesquite Hills reduced to one lane between US-54 and Red Man. Flaggers will be on-site directing traffic as needed for haul trucks crossing Mesquite Hills
- Flaggers will be on site directing traffic as needed for haul trucks crossing at McCombs and Stan Roberts.
Crews will be transporting earth embankment into the project.
Continuous closure beginning at 4 a.m. Saturday, February 21 to 6 a.m. Monday, February 23 (50 hour closure)
- Martin Luther King (FM-3255) north- and south-bound between Stan Roberts (FM-2529) and O’Hara Road (NM-404)
- Local traffic will be allowed to access businesses and residences between O-Hara Road and the Texas/New Mexico State Line.
- Traffic will be detoured using NM-404, I-10, Loop 375 (Woodrow Bean/Transmountain), and US-54.
Crews will be working on a traffic switch to allow for construction of Martin Luther King new road configuration.
Safety Lighting on Mesa (SH-20) & Dyer St. (BU-54)
Monday, February 2 to Friday, February 6
9 a.m. to 4 p.m.
- Mesa at Resler westbound right lane closed
- Mesa at Camile westbound right lane closed
- BU-54 Dyer northbound between Edge of Texas and Mesquite Hills shoulder closed
- Hercules between US-54 and Railroad eastbound right lane closed
Crews will be working on lighting improvements.
Runaway Truck Ramp
Monday, February 2 through Friday, February 6
9 a.m. to 5 p.m.
- Loop 375 (Transmountain) east- and westbound between Northwestern and I-10 left lane closed
Crews will be installing arrest system.
Bridge Replacement at Alps Dr., Hollings St., and Concepcion St.
Continuous Closure Until Further Notice 24/7
- Concepcion between Alameda and Paisano east- and westbound closed
- Alps between Marie Tobin and Raymond Telles closed
- Hollings between Raymond Telles and Hondo Pass closed
Detour: Please follow and proceed with detours in the area.
Crews will be working on culvert and bridge rehabilitation.
Road Repair
Monday, February 2 through Friday, February 6
9 a.m. to 4 p.m.
- US-62/180 Paisano eastbound alternate lane closure
- Between Mesa and Sunset eastbound alternate late closure
Crews will be working on spall.
Guardrail Repair
9 a.m. to 4 p.m.
Monday, February 2
- I-10 westbound between Viscount and Airway left lane and off-ramp at Airway closed
Tuesday, February 3
- Loop 375 (Border Highway) eastbound between Paisano and Weight Station right lane and off-ramp at Weight Station closed
Wednesday, February 4
- US-54 east- and westbound between Cassidy and Montana alternate shoulder closures
Thursday, February 5
- CD lanes (US-54) between Cassidy and Fred Wilson right lane closed
Friday, February 6
- I-10 westbound between Geronimo and Paisano right lane and off-ramp at Paisano closed
Maintenance
Monday, February 2 to Friday, February 6
9 a.m. to 4 p.m.
- Ramp N between Loop 375 East and US-54 North closed
- Loop 375 (Border Highway) eastbound between Cordova Bridge and US-54 right lane closed
- Delta eastbound between Cordova Bridge and Boone right lane closed
Crews will be working on bridge joints.