Artcraft Project

Tuesday, Sept. 8 – Friday, Sept. 11

9 a.m. – 4 p.m.

  • Redd exit ramp on I-10 eastbound full closure

Crews will be placing form work for caps.

Thursday, Sept. 10

9 p.m. – 6 a.m.

  • I-10 east and westbound between Transmountain and Artcraft full closure

Crews will be placing concrete bridge deck.

Upcoming Closure

Thursday, Sept. 17

9 p.m. – 6 a.m.

  • I-10 east and westbound between Transmountain and Artcraft full closure

Crews will be placing concrete bridge deck.

Tuesday, Sept. 8– Friday, Sept. 11

9 a.m. - 4 p.m. (As Needed)

  • SH-178 (Artcraft) east and westbound between New Mexico State Line and Doniphan alternate lane closures

Crews will be working on ITS/Illumination and MSE wall installation.

  • North Desert between Helen of Troy and Cheddars Restaurant alternate lane closures
  • South Desert between Charlie Clark Nissan and Blue Sky alternate lane closures

Crews will be forming bent caps.

  • I-10 west and eastbound between Redd and Transmountain alternate lane closures

Crews will be working on median columns steel and erecting formwork.

  • I-10 eastbound at Redd exit ramp full closure

Crews will be placing form work for caps.

Monday, March 9 (Continuous Closure Until Further Notice 24/7)

  • I-10 westbound exit ramp to Transmountain closed
  • Secondary temporary exit ramp to Transmountain open

Crews will be working on various constructions

Monday, August 31 Continuous Closure (8 week closure)

  • Paseo Del Norte Plaza access via Artcraft closure

Crews will be installing a water main.

Monday, August 10 Continuous Closure (4 – 6 week closure)

  • Intersection of Berringer through Artcraft access closure

Detour: Artcraft westbound traffic must exit at Doniphan and turn right, then proceed on Doniphan and turn right on East Borderland, then continue and turn right on Berringer.

Crews will be working on a water main bore.

Monday, June 1 Continuous Closures (8 to 9 week closure)

  • Santiago at Artcraft intersection closed

Crews will be working on a water main, storm drain, and paving.

Borderland Expressway Phase 2 Project

Tuesday, Sept. 8 – Friday, Sept. 11

Daily, 6 a.m. - 6 p.m.

  • US-54 east and westbound between Mesquite Hills and McCombs alternate lane closures
  • Mesquite Hills reduced to one lane between US-54 and Red Man
  • Flaggers will be on-site directing traffic as needed for haul trucks crossing Mesquite Hills

Daily, 7 a.m. – 5 p.m.

  • Flaggers will be on-site directing traffic as needed for haul trucks crossing at McCombs and Stan Roberts intersection

Crews will be working on bridge work and transporting earth embankment into the project.

Bridge Rehabilitation from Spur 1966 (Schuster) to Coldwell St. Project

Full Closure Until October 16, 2026 - 24/7

  • Paisano east and westbound between Spur 1966 (Schuster) and Coldwell St. main lanes closed

Crews will be working on bridge repairs.

ITS on Bridge of the Americas and Zaragoza Port of Entry Project

Monday, Sept. 8 – Friday, Sept. 11

9 a.m. - 4 p.m.

  • Loop 375 (Border Highway) eastbound between Zaragoza and Padres right lane and shoulder closed
  • Loop 375 (Border Highway) westbound between Padres and Zaragoza entrance ramp closed
  • Loop 375 (Border Highway) westbound between Padres and Zaragoza right lane and shoulder closed
  • Loop 375 (Border Highway) eastbound between Midway and Columbia Apartments right lane and shoulder closed
  • Loop 375 (Border Highway) eastbound between Fonseca and Midway right lane and shoulder closed
  • US-54 southbound between Cambridge and Altura shoulder and right lane closed
  • Loop 375 eastbound at South Americas right lane and shoulder closed
  • Loop 375 westbound at South Americas right lane and shoulder closed

Crews will be working on structures.

Safety Improvements

Median and Sidewalks at SH-20, BU-54A, IH-10, and McCombs

Tuesday, Sept. 8 - Friday, Sept. 11

7 a.m. - 4 p.m.

  • Alameda (SH-20) east and westbound between Tanton and Passmore right lane closed
  • I-10 Frontage Road east and westbound between Geronimo and Airway

Crews will be working on prepping, blading, forming, and placing rebar for concrete placement.

Traffic Signal Improvements – Loop 478 at Yandell and Montana at Trowbridge

Tuesday, Sept. 8 – Friday, Sept. 11

7 a.m. - 4 p.m.

  • Montana all directions between Chelsea Street and McAffee Place right lane closed
  • Trowbridge all directions between Paisano and Forest Way right lane closed

Crews will be performing demolition and layout of new corners for the ADA ramps and the adjustments for the new traffic signals and PED poles.

Loop 375 Rehabilitation Project

Tuesday, Sept. 8 – Thursday, Sept. 10

8 p.m. - 6 a.m. (Nightly)

  • Loop 375 (Border Highway) west and eastbound between Fonseca and Oregon full closure
  • Loop 375 (Border Highway) westbound exit ramp to Paisano (Exit 20) full closure
  • Loop 375 (Border Highway) westbound exit ramp to US-54 East and I-10 West one lane closure

Crews will be working on milling, paving, and guardrail.

Wednesday, Sept. 9 and Thursday, Sept. 10

6 a.m. – 8 p.m. (Daily)

  • Loop 375 (Border Highway) westbound off ramp to US-54 eastbound and I-10 westbound one lane closure

Crews will be working on guardrail.

BU-54A Safety Improvements

Tuesday, Sept. 8 – Friday, Sept. 4

Daily, 9 a.m. – 4 p.m.

  • Diana northbound at Vulcan between Meade and Riley left lane closed

Crews will be working on concrete work and traffic signal installations.

Road Repair

9 p.m. – 6 a.m. (Night)

Tuesday, Sept. 8

  • I-10 east between Copia and Raynolds two right lanes closed
  • Copia entrance Ramp to I-10 east closed

Wednesday, Sept. 9

  • I-10 eastbound between Viscount and Hawkins alternate lane closure

Thursday, Sept. 10

  • I-10 westbound between Viscount and Hawkins alternate lane closure

Concrete Work

Tuesday, Sept. 8 – Friday, Sept. 11

9 a.m. – 4 p.m.

  • I-10 westbound between Schuster and Executive right lane closed

Crews will be pouring concrete rip rap.

Guardrail Repair

9 a.m. – 4 p.m.

Tuesday, Sept. 8

  • Loop 375 westbound (Transmountain/Woodrow Bean) at Railroad right lane closed

Wednesday, Sept. 9

  • Loop 375 (Border Highway) between Fonseca and US-54 right lane closed

Thursday, Sept. 10

  • SH-20 Doniphan westbound between La Union and Chanate right lane closed

Friday, Sept. 11

  • Loop 375 (Transmountain) eastbound at Northwestern left lane closed

Maintenance

Tuesday, Sept. 8– Sunday, Sept. 13

9 a.m. - 4 p.m.

  • Ramp C at US-54 North to I-10 West closed

Crews will be trimming trees.

  • I-10 East between Mesa and Resler left lane closed

Crews will be cleaning.

5 a.m. - 4 p.m.

Sunday, Sept. 13

  • US-54 South two right lanes closed
  • Exit 21A closed
  • I-10 East between US-54 and Raynolds right lane closed
  • Raynolds exit closed

Sunday, Sept. 20

  • US-54 South two right lanes closed
  • Exit 21A closed
  • US-54 North between I-10 and Yandell right lane closed

Crews working on bridge joints.

Please follow the detour signs in place on all projects. All work is dependent upon weather conditions.

Media contact