Loop 1604 North Expansion lane closures
Throughout construction of these improvements, drivers will experience temporary traffic shifts and overnight lane closures on the mainlanes and frontage roads, as well as temporary daytime and overnight ramp closures.
Daytime work is anticipated to take place Mondays through Saturdays, while nighttime work and any necessary lane closures are anticipated to take place between 9 p.m. and 5 a.m., Sunday evenings through Friday mornings.
Permanent and temporary digital message boards placed along the route will alert drivers in real-time to lane closures, traffic congestion and construction activity.
This page is updated weekly. To find the most up to date and current lane closures, follow us on the San Antonio TxDOT Facebook and X pages or visit the San Antonio District’s Go Ahead! Blog
All closures are subject to change due to weather or other unforeseen circumstances.
Weekly lane closures as of March 28, 2025
Segment 1 | SH 16 (Bandera Rd.) to I-10
Weeknight lane closures
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and Hausman Road intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and Kyle Seale Parkway intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and Babcock Road intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and Chase Hill Boulevard intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and La Cantera Parkway/John Peace Boulevard intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound frontage road lane closure from John Peace Boulevard/La Cantera Parkway to I-10 for flyover ramp bridge construction. Nightly frontage road closure. Only one frontage lane closure to occur per direction. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road lane closure from the I-10 interchange to John Peace Boulevard/La Cantera Parkway for flyover ramp bridge construction. Nightly frontage road closure. Only one frontage lane closure to occur per direction. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane closure from Bandera Road (SH 16) to Kyle Seale Parkway for paving operations. Nightly mainlane closure. Only one mainlane closure to occur per direction. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane closure from Kyle Seale Parkway to Bandera Road (SH 16) for paving operations. Nightly mainlane closure. Only one mainlane closure to occur per direction. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane exit ramp to La Cantera Parkway closure for flyover ramp bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane exit ramp to I-10 eastbound closure for flyover ramp bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road entrance ramp from I-10 closure for flyover ramp bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound mainlane exit ramp closure to Loop 1604 westbound for westbound bypass bridge construction at Leon Creek. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from I-10 westbound to Loop 1604 westbound for westbound bypass bridge construction at Leon Creek. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound mainlane closure from Bandera Road (SH 16) to I-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closure. One lane to remain open at all times. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound mainlane closure from I-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closure. One lane to remain open at all times. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound frontage road lane closure from Bandera Road (SH 16) to I-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound frontage road lane closure from I-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
Weekday lane closures
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Alternating Loop 1604 eastbound frontage road lane closure from Bandera Road (SH 16) to I-10 for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Alternating Loop 1604 westbound frontage road lane closure from I-10 to Bandera Road (SH 16) for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound to westbound turnaround closure at Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound to eastbound turnaround closure at Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound to eastbound turnaround closure at Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound to westbound turnaround closure at Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound to westbound turnaround closure at Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound to eastbound turnaround closure at Kyle Seale Parkway for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound to eastbound turnaround closure at La Cantera Parkway/John Peace Boulevard for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
Weekend lane closures
- none
Long-term closures
- Sunday, March 30 until Monday, April 7. Daily/Nightly. 24 hours a day. Loop 1604 westbound to eastbound turnaround closure at La Cantera Parkway/John Peace Boulevard for retaining wall construction. Only one turnaround to be closed at a time on each direction.
- Sunday, March 30 until Monday, April 7. Daily/Nightly. 24 hours a day. Loop 1604 eastbound to westbound turnaround closure at Kyle Seale Parkway for bridge and retaining wall construction. Only one turnaround to be closed at a time on each direction.
- Sunday, March 30 until Monday, April 7. Daily/Nightly. 24 hours a day. Loop 1604 westbound to eastbound turnaround closure at Chase Hill Boulevard/Brennan Avenue for bridge and retaining wall construction. Only one turnaround to be closed at a time on each direction.
- Sunday, March 30 until Monday, April 7. Daily/Nightly. 24 hours a day. Loop 1604 eastbound frontage road right-turn lane closure from Kyle Seale Parkway to Babcock Road for bridge construction. One lane to remain open at all times.
Segment 2 | Loop 1604 and I-10 Interchange
Weeknight lane closures
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Alternating I-10 eastbound frontage road lane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Alternating I-10 westbound frontage road lane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Alternating I-10 eastbound mainlane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating mainlane closure. One lane to remain open at all times. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Alternating I-10 westbound mainlane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating mainlane closure. One lane to remain open at all times. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane exit ramp closure to I-10 eastbound for concrete barrier installation. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 westbound mainlane exit ramp closure to Loop 1604 eastbound for concrete barrier installation. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from I-10 eastbound to Loop 1604 eastbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound bypass lane closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from Loop 1604 eastbound to I-10 westbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound frontage road closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound frontage road right turn closure to Loop 1604 westbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road right turn closure to I-10 westbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound frontage road closure from the Loop 1604 interchange to UTSA Boulevard for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane closure from La Cantera Parkway to Vance Jackson Road for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane closure from Vance Jackson Road to La Cantera Parkway for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound mainlane closure from La Cantera Parkway to UTSA Boulevard for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 Westbound mainlane closure from UTSA Boulevard to La Cantera Parkway for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound frontage road closure at the Loop 1604 interchange for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 westbound frontage road closure at the Loop 1604 interchange for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound mainlane exit ramp closure to Loop 1604 westbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from I-10 westbound to Loop 1604 westbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound bypass lane closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from Loop 1604 westbound to I-10 eastbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane exit ramp closure to I-10 westbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 westbound frontage road closure from the Loop 1604 interchange to La Cantera Parkway for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road closure from Vance Jackson Road to the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane exit ramp closure to I-10 westbound for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 9 p.m. until 5 a.m. I-10 westbound frontage road closure from the Loop 1604 interchange to La Cantera Parkway for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Monday, April 7. Weeknights. 10:30 p.m. until 5 a.m. I-10 westbound exit ramp closure to La Cantera Parkway for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Friday, April 7. Weeknights. 10 p.m. until 5 a.m. Loop 1604 westbound frontage road closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
- Sunday, March 30 until Friday, April 7. Weeknights. 10 p.m. until 5 a.m. Loop 1604 westbound exit ramp closure just before the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
Weekday lane closures
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Alternating I-10 eastbound frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete barrier installation. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Alternating I-10 westbound frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete barrier installation. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound frontage road closure at the I-10 interchange for bridge construction. Daily closure. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound frontage road closure at the I-10 interchange for bridge construction. Daily closure. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. I-10 westbound to eastbound turnaround closure at La Cantera Parkway for bridge construction. Daily closure. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. I-10 westbound frontage road right lane closure from La Cantera Parkway to Worth Parkway for utility work. Daily closure. Excluding weekends.
- Monday, March 31 until Monday, April 7. Weekdays. 9 a.m. until 3 p.m. I-10 westbound frontage road right lane closure from UTSA Boulevard to the Loop 1604 interchange for utility work. Daily closure. Excluding weekends.
Weekend Closures
- Friday, March 28 until Monday, March 31. Weekend nights. 9 p.m. until 5 a.m. I-10 eastbound frontage road closure from Via La Cantera to the Loop 1604 interchange for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Friday, March 28 until Monday, March 31. Weekend nights. 9 p.m. until 5 a.m. I-10 eastbound bypass lane closure at the Loop 1604 interchange for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Friday, March 28 until Monday, March 31. Weekend nights. 9 p.m. until 5 a.m. I-10 westbound mainlane closure at the Loop 1604 interchange for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Friday, March 28 until Monday, March 31. Weekend nights. 9 p.m. until 5 a.m. I-10 westbound bypass lane closure at the Loop 1604 interchange for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Friday, March 28 until Monday, March 31. Weekend nights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from I-10 eastbound to Loop 1604 eastbound for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Friday, March 28 until Monday, March 31. Weekend nights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from I-10 westbound to Loop 1604 westbound for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Friday, March 28 until Monday, March 31. Weekend nights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from Loop 1604 westbound to I-10 eastbound for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Saturday, March 29 until Sunday, March 30. Weekend daytime. 5 a.m. until 9 p.m. I-10 eastbound frontage road closure from Via La Cantera to the Loop 1604 interchange for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Saturday, March 29 until Sunday, March 30. Weekend daytime. 5 a.m. until 9 p.m. I-10 eastbound bypass lane closure at the Loop 1604 interchange for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Saturday, March 29 until Sunday, March 30. Weekend daytime. 5 a.m. until 9 p.m. Ramp/cloverleaf closure from Loop 1604 westbound to I-10 eastbound for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
- Saturday, March 29 until Sunday, March 30. Weekend daytime. 5 a.m. until 9 p.m. Ramp/cloverleaf closure from I-10 eastbound to Loop 1604 eastbound for bridge construction. Law enforcement will direct traffic through intersections during this time, as needed. Lanes are expected to remain closed for the duration.
Long-term closures
- Sunday, March 30 until Monday, April 7. Daily/Nightly. 24 hours a day. I-10 eastbound frontage road and La Cantera Parkway intersection alternating inside/outside lane closure for roadway construction.
- Sunday, March 30 until Monday, April 7. Daily/Nightly. 24 hours a day. Loop 1604 eastbound frontage road right turn closure to the I-10 eastbound frontage road for roadway construction.
- Sunday, March 30 until Monday, April 7. Daily/Nightly. 24 hours a day. I-10 eastbound frontage road closure just south of Loop 1604 for bridge construction.
- Sunday, March 30 until Monday, April 7. Daily/Nightly. 24 hours a day. I-10 westbound to eastbound turnaround closure at La Cantera Parkway intersection for drainage installation.
Segment 3 | I-10 to US 281
Weeknight lane closures
- Sunday, March 30 until Friday, April 4. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound mainlane closure from the US 281 exit ramp to Tradesman Drive for barrier setting and striping. Nightly alternating mainlane closures. Excluding weekends.
- Sunday, March 30 until Friday, April 4. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound mainlane closure from Tradesman Drive to US 281 exit ramp for barrier setting and striping. Nightly alternating mainlane closures. Excluding weekends.
- Sunday, March 30 until Friday, April 4. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound frontage road closure from I-10 to the US 281 exit ramp for barrier setting and striping. Nightly alternating mainlane closures. Excluding weekends.
- Sunday, March 30 until Friday, April 4. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound frontage road closure from US 281 to the I-10 exit ramp for barrier setting and striping. Nightly alternating mainlane closures. Excluding weekends.
- Monday, March 31 until Thursday, April 3. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound frontage road closure from I-10 to Vance Jackson Road for flyover construction.
- Monday, March 31 until Thursday, April 3. Weeknights. 9 p.m. until 5 a.m. Vance Jackson southbound lanes closure from Loop 1604 eastbound frontage road to westbound frontage road for flyover construction.
- Monday, March 31 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane closure from the Blanco Road exit ramp to the Blanco Road entrance ramp for bridge construction.
- Monday, March 31 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. Blanco Road northbound and southbound closures from Loop 1604 westbound frontage road to Madera Parkway for drainage work.
- Monday, March 31 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. NW Military Highway northbound and southbound lane closures at the Loop 1604 interchange.
- Monday, March 31 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound to eastbound turnaround closure at NW Military Highway for drainage work.
- Monday, March 31 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road closure from Bitters Road to the NW Military Highway exit ramp for drainage work.
- Thursday, April 3 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound frontage road closure from Vance Jackson Road to Tradesman Drive for flyover construction.
- Thursday, April 3 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. Tradesman Drive northbound and southbound lane closures at the Loop 1604 interchange for flyover construction.
Weekday lane closures
- Tuesday, April 1 until Wednesday, April 2. Daytime closure. 9 a.m. until 3 p.m. Northbound Blanco Road right lane closure from Country Club Lane to Talavera Parkway for SAWS work.
Weekend lane closures
- Friday, April 4 until Monday, April 7. Weekend closure. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane closure from the Stone Oak Parkway exit ramp to the Stone Oak Parkway entrance ramp for pavement work.
Long-term closures
- none
Segment 4 | US 281 to Redland Rd.
Weeknight closures
- Sunday, March 30 until Saturday, April 12. Weeknights. 9 p.m. until 5 a.m. US 281 northbound and southbound frontage road closure (both directions, including turnarounds) at the Loop 1604 intersection for bridge construction. Nightly closure.
- Sunday, March 30 until Friday, April 18. Weeknights. 9 p.m. until 5 a.m. Stone Oak Parkway northbound and southbound intersection closure (both directions, including turnarounds) for bridge construction. Nightly closure, excluding weekends.
- Monday, March 31 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. US 281 northbound mainlane closure from Donnella Drive to Redland Road for bridge construction. Nightly closure, excluding weekends.
- Monday, March 31 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. US 281 southbound mainlane closure from Redland Road to Donella Drive for bridge construction. Nightly closure, excluding weekends.
- Monday, March 31 until Saturday, April 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane closure between US 281 and Gold Canyon Road for bridge construction. Nightly closure, excluding weekends.
Weekday closures
- Monday, March 31 until Thursday, April 10. Weekdays. 9 a.m. until 3 p.m. US 281 turnaround closure between Loop 1604 westbound and eastbound frontage roads for wall construction. Daily Closure.
- Monday, March 31 until Friday, May 2. Weekdays. 9 a.m. until 4 p.m. Loop 1604 westbound to eastbound frontage road turnaround closure at Stone Oak Parkway for bridge construction. Daily closure.
- Monday, March 31 until Friday, May 2. Weekdays. 9 a.m. until 4 p.m. Loop 1604 eastbound to westbound frontage road turnaround closure at Stone Oak Parkway for bridge construction. Daily closure.
- Monday, March 31 until Friday, April 11. Weekdays. 9 a.m. until 3 p.m. Gold Canyon Road northbound frontage road right turn lane closure to Loop 1604 eastbound frontage road for signal work. Daily Closure.
- Monday, March 31 until Friday, April 11. Weekdays. 9 a.m. until 3 p.m. Gold Canyon Road northbound right shoulder closure at the Loop 1604 intersection for signal work. Daily Closure.
- Monday, March 31 until Friday, April 11. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound frontage road right turn lane closure between Tuscany Stone and Stone Oak Parkway for signal work. Daily Closure.
Weekend closures
- Friday, April 11 until Monday, April 14. Weekend closure. 9 p.m. until 5 a.m. US 281 northbound frontage road closure at the Loop 1604 intersection for bridge construction.
- Friday, April 11 until Monday, April 14. Weekend closure. 9 p.m. until 5 a.m. US 281 southbound frontage road closure at the Loop 1604 intersection for bridge construction.
- Friday, April 11 until Monday, April 14. Weekend closure. 9 p.m. until 5 a.m. Loop 1604 eastbound to westbound turnaround closure at the US 281 intersection for bridge construction.
- Friday, April 11 until Monday, April 14. Weekend closure. 9 p.m. until 5 a.m. Loop 1604 westbound to eastbound turnaround closure at the US 281 intersection for bridge construction.
- Friday, April 11 until Monday, April 14. Weekend closure. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane closure from US 281 to Gold Canyon Road for bridge construction.
- Saturday, April 5 from 9 a.m. until 4 p.m. Weekend closure. One day only. Loop 1604 westbound to eastbound turnaround closure at Stone Oak Parkway for bridge construction.
- Saturday, April 12 from 9 a.m. until 4 p.m. Weekend closure. One day only. Loop 1604 westbound to eastbound turnaround closure at Stone Oak Parkway for bridge construction.
- Saturday, April 19 from 9 a.m. until 4 p.m. Weekend closure. One day only. Loop 1604 westbound to eastbound turnaround closure at Stone Oak Parkway for bridge construction.
- Saturday, April 26 from 9 a.m. until 4 p.m. Weekend closure. One day only. Loop 1604 westbound to eastbound turnaround closure at Stone Oak Parkway for bridge construction.
- Saturday, May 3 from 9 a.m. until 4 p.m. Weekend closure. One day only. Loop 1604 westbound to eastbound turnaround closure at Stone Oak Parkway for bridge construction.
Segment 5 | Redland Rd. to Judson Rd.
Weeknight closures
- Monday, March 31 until Friday, April 4. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound frontage road closure from Judson Road to Bulverde Road for barrier placement. One lane to remain open at all times. Loop 1604 westbound frontage road closure and the Loop 1604 westbound mainlane closure will not occur simultaneously.
- Monday, March 31 until Friday, April 4. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound frontage road closure from Bulverde Road to Judson Road for barrier placement. Nightly alternating frontage road closure. One lane to remain open at all times. Loop 1604 eastbound frontage road closure and the Loop 1604 eastbound mainlane closure will not occur simultaneously.
- Monday, March 31 until Friday, April 4. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane closure from Bulverde Road to Judson Road for barrier placement.
Weekday closures
- none
Weekend closures
- none
Long-term closures
- Monday, March 31 until Friday, April 4. 9 a.m. until 5 p.m. Loop 1604 westbound to eastbound full turnaround closure at Bulverde Road for barrier placement.