Additional key considerations
Skip to main content

Segment 2 - additional key considerations

Key information

This segment will improve the I-45 mainlanes and frontage roads from I-10 north to I-610 and rebuild the I-45/I-610 interchange

  • Widen I-45 in this area to accommodate four MaX (Managed Express) lanes. The proposed roadway would include ten general purpose lanes (five in each direction), four MaX lanes (two in each direction), and two to three frontage road lanes in each direction.
    • The MaX lanes would increase the High Occupancy Vehicle) space in the middle of the I-45 mainlanes from one lane to four. Only buses and vehicles with two or more people in them would be able to travel in the MaX lanes.
  • The proposed I-45 and I-610 frontage roads would be continuous at the I-45/I-610 interchange.
  • The mainlanes will be depressed between Cottage and N. Main streets, providing an opportunity to build a structural cap which could be funded and developed by others.
  • TxDOT is studying how to potentially reduce the roadway footprint of this project.
  • I-45 NHHIP proposes significant drainage improvements in accordance with new Atlas 14 standards issued by NOAA.

Project map

Design considerations details

Bicycle/pedestrian

1.)

Channel improvements and bike trail along channel being incorporated (north of Wrightwood St.)

2.)

Potential pedestrian bridge being evaluated over North St.

3.)

Channel improvements and bike trail along channel being evaluated (northbound and southbound before Patton St.)

4.)

Channel improvements and bike trail along channel being incorporated (southbound from Link St to Coronado St.)

5.)

Channel improvements and bike trail along channel being incorporated (along Little White Oak Bayou just north of I-610)

6.)

Channel improvements and bike trail along channel being incorporated (east of I-45)

Mobility

7.)

I-10 eastbound direct connector going to I-45 northbound mainlanes instead of frontage road being evaluated

8.)

Potential U-turn from I-45 northbound frontage road at N. Main St. being evaluated

9.)

I-45 northbound entrance ramp from N. Main St. being evaluated

10.)

I-45 southbound exit ramp to N. Main St. being evaluated

11.)

Cottage St. closure being evaluated due to safety concerns if N. Main St. entrance/exit ramps are provided

12.)

Bridge over Patton St. slightly extended northbound

13.)

Extend Segment 2 limit to north of Airline Drive being evaluated for construction phasing and drainage purposes

Flooding mitigation

14.)

Replace existing culvert with bridges, providing drainage improvements

15.)

Add new detention ponds along I-45 northbound frontage road before Patton St., providing drainage improvements

16.)

Replace existing culvert with a bridge, providing drainage improvements