Segment 3A - temporary mainlane bridges & Wheeler Transit Center
Skip to main content

Segment 3A - temporary mainlane bridges & Wheeler Transit Center

Overview

During Segment 3A Construction, traffic will still need to move through the area. Below is the rationale for why TxDOT made the decision to build temporary bridges.

Temporary I-69 mainlane bridges of three lanes in each direction and 38 feet wide would accommodate traffic during construction

Challenges with using existing I-69 bridges

  • Reduces existing travel lanes to 2 narrow lanes in each direction for up to 5 years
  • Requires major foundation improvements to prevent weakening structures during construction of below grade mainlanes, increasing construction time and costs
  • Requires a continuous wall to be built down the middle of the freeway for the length of the project
  • Still requires some temporary bridge construction

The benefits of constructing temporary bridges *:

  • Allows 3 travel lanes in both directions to be maintained
  • Significantly reduces the impacts to the traveling public
  • Improves safety by isolating traffic away from the construction zone
  • Reduces overall construction time by significantly reducing the number of lane closures needed
  • Reduces number of lane reconfigurations, reducing the potential for driver confusion
  • Allows the contractor to build street-level caps/bridges and the depressed mainlane roadway more efficiently
  • Makes use of additional needed right of way

* In both directions for the length of the project

This Segment 3A map shows the proposed temporary mainlane bridges in purple, outside the existing I-69 mainlanes.

I-69 temporary mainlane bridges from Main St. to Caroline St.

Northbound and southbound temporary mainlane bridge typical section

Reconstruction of the METRO Wheeler Transit Facilities along Fannin St. requires additional right of way.

  • New transit center light rail alignment across I-69 is shown in red on the image to the left
  • Not disrupting transit center operations achieved by building additional track and replacing existing tracks in phases
  • Reconstruction will provide new station, enhanced bus turnouts, bus bays, sidewalks, and a bus-only connection between Fannin and Main streets also shown on the left
  • The areas circled in orange on the left represent additional right of way needed